Development Of Risk-Based Audit Method Standard For Stadium Project Using Design And Build Contract To Minimize Dispute From Construction Management Point Of View

  • Ega Alvian Sutekat Civil Engineering Faculty, Universitas Indonesia, Depok 16424, Indonesia
  • Anggoro Putro Civil Engineering Faculty, Universitas Indonesia, Depok 16424, Indonesia
  • Yusuf Latief Civil Engineering Faculty, Universitas Indonesia, Depok 16424, Indonesia
Keywords: Project Management, Design and Build, Standards for Inspection of Works, and Construction Management and Dispute.

Abstract

The Design and Build method have been widely used in government projects in recent years. The
construction of a sports stadium is one type of project that uses an integrated contract. Design and
build, which is considered to have high complexity and is urgent, so the use of the Design and Build
method is expected to provide a solution in the implementation of the project. However, in
implementing the integrated design and construction contract, there are still many disputes from
stakeholders involved such as Inspection of Work Results. This study aims to identify the factors that
cause dispute in the Design and Build project and develop a Standard for Inspection of Work Results
from the perspective of Construction Management. The results of the study indicate the factors
causing the dominant risk-based dispute as well as corrective action in the form of standard
inspection of work results on construction projects.

Downloads

Download data is not yet available.

References

Anggoro. (2020). Pengembangan Standard Measurement Method Berbasis WBS pada Kontrak Terintegrasi

Rancang Bangun Gedung Negara untuk Menurunkan Dispute.

Anggraini, A. (2019). Pengembangan Standar Work Breakdown Structure (WBS) Berbasis Risiko Untuk

Perencanaan Safety Pada Pekerjaan Konstruksi Stadion. Depok.

Badan Pemeriksa Keuangan RI. (2013). Seri Panduan Pemeriksaan Pengadaan Barang dan Jasa - Infrastruktur.

Jakarta.

Geraint John, R. S. (2013). Stadia the Populous Design and Development Guide.

Kementrian Pekerjaan Umum dan Perumahan Rakyat Badang Pengembangan Sumber Daya Manusia. (2016).

Biaya Pembangunan Gedung Negara.

Kumar, R. (2011). Research Methodology.

Masuin, R., & Latief, Y. (2019). Development of integration risk on integrated management system in order to

increase organizational performance of construction company.

Perdana, T. C. (2017). Pengembangan Pedoman Manajemen Klaim Pada Proyek Design - Build Berbasis Risiko

Untuk Meminimalkan Dispute.

PMBOK 6th Editions. (2017). Project Management Body of Konowledge 6th Edition. Pennsylvania: Project

Management Institute, Inc.

Salako. (2010). Risk Classification Model for Design and Build Projects.

Simanjuntak, M. R., & Sudibyo, B. (2020). Identification Of Risk Factors And Variables Of Design And Build

Contracts In The Semanggi Interchange Project.

Suharyanto, A., & Simanjuntak, M. R. (2020). Risk identification of Design And Build at school building

construction project in central jakarta.

Sukrisno, A. (2012). Auditing Petunjuk Praktis Pemeriksaan Akuntan Oleh Akuntan Publik. Jakarta.

Suyoga, I. M., & Usfunan, Y. (2020). Penyelesaian Sengketa Kontrak Kerja Konstruksi Melalui Ajudikasi Dan

Perbandingan Dengan Arbitrase.

Published
2023-07-22
How to Cite
Alvian Sutekat, E., Putro, A., & Latief, Y. (2023). Development Of Risk-Based Audit Method Standard For Stadium Project Using Design And Build Contract To Minimize Dispute From Construction Management Point Of View. International Journal of Science, Technology & Management, 4(4), 774-779. https://doi.org/10.46729/ijstm.v4i4.863
Section
Articles